June 2, 2023
Project work was delayed by the wet conditions in May. The contractor will be onsite starting on June 5 at all project locations. The contractor will work through the final grading, restoration, and punch list items at all four project locations. The work is expected to take approximately one week.
Please use caution and expect some construction traffic and delays in these locations.
May 8, 2023
The contractor will be onsite starting on May 9 at all project locations. The contractor will work through the final grading, restoration, and punch list items at all four project locations. The work is expected to take approximately two weeks.
Please use caution and expect some construction traffic and delays in these locations.
May 2, 2023
The contractor is expected to complete topsoil placement, final grading, restoration, and vegetation establishment work at all project locations this month as weather conditions allow. Punch list items will also be worked on. Work is anticipated to start on Monday, May 8, 2023.
Project Location - Basin RM-P4.9 (On Lake Dr. E just east of Great Plains Blvd) – Tree planting is expected to start on Monday, May 8, 2023, and should be completed within the week. Trees will be staked on Wednesday, 5/3/2023.
Please use caution and expect some construction traffic and delays in these locations.
March 3, 2023
Project Location - Basin RM-P4.9 (On Lake Dr E just east of Great Plains Blvd) – Work on this site was delayed by the recent snowstorm and warmer weather. The contractor is currently wrapping up the storm sewer improvements. Some additional grading and hauling are expected to be completed the week of March 6, 2023. Grading Substantial competition at this location is expected by the end of mid-March.
Project Location - Basin BC-P5.9 (Bandimere Park) – Work at this location is complete. Please remember that some punch list items may soon be needed at this location. Trail closures during working hours at the park are anticipated. The skating rink and other park amenities will remain open during construction.
Project Location - Basin LR-P1.6 (Off of Lyman Blvd and East of Great Plains Blvd) – Work at this project location is complete. Please remember that some punch list items may soon be needed at this location.
Project Location - Basin LR-P1.7B (Off of Lyman Blvd just south of Riley Ridge Park)– Work at this project location is substantially complete. Please remember that some punch list items may soon be needed at this location.
Please use caution and expect some construction traffic and delays in these locations.
February 17, 2023
Project Location - Basin RM-P4.9 (On Lake Dr. E just east of Great Plains Blvd) – The contractor is currently working on excavation and hauling off material. Hauling is expected to be completed on Wednesday, February 22, 2023, but depends on weather conditions. Grading and pipework are also scheduled for the week of 2/20/23. Substantial competition at this location is expected by the end of February.
Project Location - Basin BC-P5.9 (Bandimere Park) – Work at this location is complete. Please remember that some punch list items may soon be needed at this location. Trail closures during working hours at the park are anticipated. The skating rink and other park amenities will remain open during construction.
Project Location - Basin LR-P1.6 (Off of Lyman Blvd and East of Great Plains Blvd) – Work at this project location is complete. Please remember that some punch list items may be needed at this location soon.
Project Location - Basin LR-P1.7B (Off of Lyman Blvd just south of Riley Ridge Park)– Work at this project location is substantially complete. Please keep in mind that some punch list items may be needed at this location soon.
Please use caution and expect some construction traffic and delays in these locations.
February 10, 2023
Project Location - Basin RM-P4.9 (On Lake Dr E just east of Great Plains Blvd) – The contractor is mobilizing to the site. The contractor will begin excavation and hauling work at this location on Monday, February 13, 2023. One to two weeks’ worth of work is anticipated at this location.
Project Location - Basin BC-P5.9 (Bandimere Park) – Work at this location is complete. Please remember that some punch list items may soon be needed at this location. Trail closures during working hours at the park are anticipated. The skating rink and other park amenities will remain open during construction.
Project Location - Basin LR-P1.6 (Off of Lyman Blvd and East of Great Plains Blvd) – Work at this project location is complete. Please keep in mind that some punch list items may be needed at this location soon.
Project Location - Basin LR-P1.7B (Off of Lyman Blvd just south of Riley Ridge Park)– Work at this project location is substantially complete. Please keep in mind that some punch list items may be needed at this location soon.
Please use caution and expect some construction traffic and delays in these locations.
January 31, 2023
The contractor has elected to modify the construction schedule to start work at Bandimere Park this week to take advantage of the favorable weather conditions.
Project Location - Basin BC-P5.9 (Bandimere Park) – The contractor will begin work at this location on Wednesday, February 2, 2023. Initial construction activities include site mobilization, site preparation, and dewatering, with excavation planned for later in the week. One to two weeks’ worth of work is anticipated at this location. Trail closures during working hours at the park are anticipated. The skating rink and other park amenities will remain open during construction.
Project Location - Basin RM-P4.9 (On Lake Dr E just east of Great Plains Blvd) – The contractor is expected to begin work at this location the week of February 6. One to two weeks’ worth of work is anticipated at this location. More details will be posted with future updates.
Project Location - Basin LR-P1.6 (Off of Lyman Blvd and East of Great Plains Blvd) – Work at this project location is substantially complete. Please keep in mind that some punch list items may be needed at this location soon.
Project Location - Basin LR-P1.7B (Off of Lyman Blvd just south of Riley Ridge Park)– The contractor plans to finish up excavation work early this week. Please keep in mind that some punch list items may be needed at this location soon.
Please use caution and expect some construction traffic and delays in these locations.
January 27, 2023
Project Location - Basin LR-P1.6 (Off of Lyman Blvd and East of Great Plains Blvd) – Work at this project location is substantially complete. Please keep in mind that some punch list items may be needed at this location soon.
Project Location - Basin LR-P1.7B (Off of Lyman Blvd just south of Riley Ridge Park) – It is anticipated that work at this location will be completed today. If it is not completed today, it is tentatively scheduled to be completed on Monday, January 30, 2023. Please keep in mind that some punch list items may be needed at this location soon.
Project Location - Basin RM-P4.9 (On Lake Dr E just east of Great Plains Blvd) – The contractor is expected to begin work at this location this upcoming Monday, January 30, 2023. One to two weeks’ worth of work is anticipated at this location.
Please use caution and expect some construction traffic and delays in these locations.
January 23, 2023
Project Location - Basin LR-P1.6 (Off of Lyman Blvd and East of Great Plains Blvd) – The contractor is onsite removing sediment and hauling out material today and tomorrow if needed. Restoration is expected to be completed by Tuesday, and It is anticipated that work will be completed at this location on Wednesday, January 25, 2023. Please keep in mind that some punch list items may be needed at this location in the near future, but the work at this pond should be substantially complete, weather permitting, this Wednesday.
Project Location - Basin LR-P1.7B (Off of Lyman Blvd just south of Riley Ridge Park) – The contractor will begin to remove sediment and haul out material on Tuesday, January 24, 2023. The remaining work and restoration are expected to be done by Wednesday, and It is anticipated that work will be completed at this location on Wednesday, January 25, 2023. Please keep in mind that some punch list items may be needed at this location in the near future, but the work at this pond should be substantially complete, weather permitting, this Wednesday.
Project Location - Basin RM-P4.9 (On Lake Dr E just east of Great Plains Blvd) – The contractor is expected to begin work at this location this Thursday, 1/26/23. One to two weeks’ worth of work is anticipated at this location. More details will be available later this week.
Please use caution and expect some construction traffic and delays in these locations.
January 11, 2023
Tree removal, clearing, and grubbing will start today at all four project sites. Mobilization at Bandimere Park is scheduled for the week of January 16.
January 9, 2023
Peterson Companies Inc. was the low bidder and was awarded the contract. Mobilization and construction activities will begin in early January.
December 2022